Section B is ready, waiting for approvals, o sections A and C they put last SMA layer
As of 05/27/2012
Section A:
- A layer of foundation and 100%
- Binder - was 99%, 99% (no change)
- A layer of SMA - was 13% is 21% (an increase of 8%)
Section B:
- A layer of foundation and 100%
- 100% binder
- A layer of SMA - was 98%, 100% (an increase of 2%)
Section C:
- A layer of foundation - was 93.7% is 99.8% (an increase of 6.1%)
- Binder - was 87% is 98.1% (an increase of 11.1%)
- SMA layer - it was 0% is 16.6% (an increase of 16.6%)
Section D:
- A layer of foundation and 100%
- Binder - 100%
- SMA layer - 100%
Section E:
- A layer of foundation - 100%,
- Binder - 100%
- 100% SMA layer
Whole A2 highway from Warsaw to German Border will be ready on 06.06.2012, section A and C (about 50 km) will be passable (means lanes are ready, not all infrastructure ready, not fully covered with last SMA layer, so speed will be limited to 80 km/h).